Excavation & Trenching Permit Generator
Fill in the excavation, the utility locates, the soil classification your competent person made and the protective system in use; the permit on the right updates as you type and prints on Letter paper or downloads as a PDF. Every line cites the paragraph of 29 CFR 1926 Subpart P it comes from.
Nothing you type is sent to our servers. A draft is kept in this browser until you clear it.
Template for informational purposes only. This document must be reviewed and adapted by a competent or qualified person for your specific jobsite, equipment, and applicable federal, state, and local requirements. It does not constitute legal, engineering, or safety advice and does not by itself establish compliance with OSHA or any other standard. SteelToeTools assumes no liability for its use. Nothing you type is sent to our servers.
How to use this permit
- 1Call before you dig, then verify in the field. Call 811 far enough ahead to meet your state's notice period, then check that the marks are in the ground, still legible and consistent with the drawings. Private lines on the property are usually not part of the ticket.
- 2Have the competent person classify the soil. At least one visual and one manual analysis (Subpart P Appendix A). When in doubt, Type C is the conservative call — and the classification has to be redone when conditions change.
- 3Record the protective system and where its design comes from. Tabulated data or an engineer's design must be at the jobsite while the excavation is open (1926.652(b)(3)-(4), (c)(2)-(4)). Our trench slope calculator gives the cut-back distance and top width for the soil type you selected.
- 4Walk the rest of the checklist before the bucket moves. Egress within 25 ft, spoil 2 ft back, traffic control, mobile equipment warning system, water, atmosphere where it applies.
- 5Print or download the PDF and sign it. Keep it with the excavation, and pair it with the daily excavation inspection form — the permit is issued once, the inspection is required every day the excavation is open.
What OSHA requires — and what it does not
There is no excavation permit in 29 CFR 1926 Subpart P. A dig permit is an industry practice: general contractors, utilities and owners use it to prove that the conditions below were checked and that a competent person was named before anyone broke ground. The requirements themselves are these.
| Requirement | Citation | On this permit |
|---|---|---|
| Surface encumbrances that create a hazard removed or supported | 1926.651(a) | Utilities & surface |
| Utility locations estimated before opening, owners contacted, exact location determined by safe and acceptable means, installations protected while exposed | 1926.651(b)(1)-(4) | Underground installations |
| Ladder, stairway or ramp within 25 ft of lateral travel in trenches 4 ft or deeper; ramps designed by a competent person | 1926.651(c)(1)-(2) | Access and egress |
| High-visibility garments for employees exposed to public vehicular traffic | 1926.651(d) | Surface hazards |
| No employee under loads handled by lifting or digging equipment | 1926.651(e) | Surface hazards |
| Warning system where mobile equipment approaches the edge without a clear view | 1926.651(f) | Surface hazards |
| Atmosphere tested before entry over 4 ft where a hazardous atmosphere exists or could reasonably be expected; 19.5% oxygen, 20% of the LFL, rescue equipment readily available | 1926.651(g)(1)-(2) | Atmospheric hazards |
| No work in accumulated or accumulating water without precautions; water removal monitored by the competent person; drainage controlled | 1926.651(h)(1)-(3) | Surface hazards |
| Support, bracing or underpinning for adjacent structures; no undermining of sidewalks and pavements | 1926.651(i)(1)-(3) | Adjacent structures |
| Faces scaled or barricaded; excavated material and equipment at least 2 ft from the edge or retained | 1926.651(j)(1)-(2) | Surface hazards |
| Daily inspections by a competent person, before the start of work, throughout the shift as needed, and after every rainstorm or other hazard-increasing occurrence | 1926.651(k)(1) | Sign-off, then the daily inspection form |
| Walkways where employees cross the excavation; guardrails at 6 ft or more above lower levels | 1926.651(l) | Access and egress |
| Protective system for every employee in the excavation, except entirely in stable rock or less than 5 ft deep with no indication of a cave-in on the competent person's examination | 1926.652(a)(1) | Protective system |
| Sloping, benching, shoring and shields designed under one of the four options; tabulated data or the engineer's design kept at the jobsite; sloping or benching over 20 ft deep designed by a registered professional engineer | 1926.652(b), (c); App. B | Basis of the design |
| Shields used within their design, employees kept out during installation, removal and vertical movement, no more than 2 ft excavated below the bottom | 1926.652(g)(1)-(2) | Shield or support system |
State Plan states and many municipalities add their own dig permit, street-cut permit and one-call notice periods on top of Subpart P. Check your state rules and the requirements of the facility owner before you dig.
Frequently asked questions
Sources & references
- 29 CFR 1926.650 — Scope, application and definitions (competent person, trench, protective system, stable rock)
- 29 CFR 1926.651 — Specific excavation requirements (utilities, egress, atmospheres, water, spoil, inspections)
- 29 CFR 1926.652 — Requirements for protective systems (sloping, shoring, shields, engineer designs)
- 29 CFR 1926 Subpart P App. A — Soil classification (one visual and one manual analysis)
- 29 CFR 1926 Subpart P App. B — Sloping and benching, Table B-1, the 20 ft engineer rule
- FCC — 811 designated as the nationwide call-before-you-dig number
- PHMSA — Call Before You Dig / one-call program
- OSHA — Trenching and Excavation safety topics page
Content checked against these sources — last reviewed August 28, 2026.