Enter the area and the depth of stone you want in the ground, pick the material, and get the tons to order, the loose cubic yards that will arrive on the truck and the compacted volume in place. Order by the ton when you can: the ton is the same number at the quarry, on the scale ticket and in the trench.
Results are estimates for planning purposes. Verify with your supplier, engineer, or a qualified professional before ordering material or performing work.
Coverage per ton, by depth
| Depth in place | ft² per ton | Tons per 100 ft² | Compacted yd³ per 100 ft² |
|---|---|---|---|
| 2 in | 89 | 1.13 | 0.62 |
| 3 in | 59 | 1.69 | 0.93 |
| 4 in | 44 | 2.26 | 1.23 |
| 6 in | 30 | 3.39 | 1.85 |
| 8 in | 22 | 4.52 | 2.47 |
| 12 in | 15 | 6.78 | 3.70 |
For ¾ in dense-graded crushed base at 1.83 tons per compacted cubic yard, the value the WisDOT study measured. Heavier or lighter material scales the tons in proportion; the cubic yards do not change. Halve the depth and you double the coverage.
The yard in the truck is not the yard in the trench
This is the mistake that puts a job a third short. Compaction changes the volume and leaves the weight alone. The same WisDOT study measured how much each material expands going from compacted in place to a loose stockpile:
| Material | Tons per compacted yd³ | Compacted → loose |
|---|---|---|
| Crushed stone base, ¾ in | 1.80–1.86 | 36–47% |
| Crushed stone base, 1¼ in | 1.79–1.98 | 34–52% |
| Crushed stone base, 3 in | 1.78–1.87 | 34–45% |
| Breaker run | 1.82–1.87 | 27–30% |
| Select crushed material | 1.77–1.81 | 27–29% |
| Granular backfill, Grade 1 or 2 | 1.62–1.66 | 38–52% |
| Structure backfill, Grade A or B | 1.50–1.72 | 35–48% |
| RAP base (asphalt millings) | 1.64–1.71 | 35–46% |
| RCA base (recycled concrete) | 1.65–1.75 | 37–60% |
Measured values from WHRP G22-05 (WisDOT, December 2023), Table 4.11. WisDOT's own statewide guideline for dense-graded base is 1.75 to 2.10 tons per cubic yard. The study also found that only about 23% of the state DOTs it surveyed publish conversion factors at all — which is why so few of these numbers are findable anywhere.
Ordering notes
- Order by the ton. A ton is the same number at the quarry, on the scale ticket and in the trench. A yard is three different numbers.
- Get your own density in ten seconds. Tons billed × 2,000 ÷ (cubic yards ordered × 27) is the lb/ft³ of that material from that supplier. Enter it in the custom field and everything after that is exact rather than typical.
- No pea gravel, river rock or decomposed granite here. Nobody publishes a defensible figure. FHWA's own soils manual spans 85 to 138 lb/ft³ for a clean sand on packing alone — a midpoint would be wrong half the time. Use the custom field with your supplier's number.
- Depth is a design decision. This page converts a depth into a quantity; it does not choose one. Traffic, subgrade and, on public work, the specification set the thickness.
- Think about where the pile goes. If the stone is being stockpiled next to an open excavation, 29 CFR 1926.651(j)(2) keeps spoil and materials at least 2 ft back from the edge, or retained. A delivered load of base is a surcharge load on the trench wall.
How it's calculated
- Area
rectangle: A = length × width · circle: A = π / 4 × diameter² · triangle: A = base × height / 2- Compacted volume in place
V (ft³) = A (ft²) × depth (in) / 12 → yd³ = ft³ / 27- Volume to buy
V order = V × (1 + extra % / 100)- Tons
tons = V order (compacted yd³) × conversion factor (tons per compacted yd³)The WisDOT conversion factors are compacted unit weights expressed in short tons per cubic yard. Measured values: dense-graded base 1.80–1.86 (¾ in), 1.79–1.98 (1¼ in), 1.78–1.87 (3 in); breaker run 1.82–1.87; select crushed 1.77–1.81; granular backfill 1.62–1.66; structure backfill 1.50–1.72; RAP base 1.64–1.71; RCA base 1.65–1.75. WisDOT's own statewide guideline range for dense-graded base is 1.75 to 2.10.- Loose cubic yards on the truck
loose yd³ = V order (compacted yd³) × (1 + expansion %)Measured compacted-to-loose expansion: 36–47% for ¾ in base, 34–52% for 1¼ in, 34–45% for 3 in, 27–30% breaker run, 27–29% select crushed, 38–52% granular backfill, 35–48% structure backfill, 35–46% RAP, 37–60% RCA. Compaction changes the volume, never the weight — which is why the ton is the safer unit to order in.- Coverage per ton
ft² per ton = 2,000 / (density (lb/ft³) × depth (in) / 12)At 4 in of ¾ in crushed base, one ton covers about 44 ft². At 2 in it covers about 89 ft²; at 6 in, about 30 ft².
Frequently asked questions
Sources & references
- WHRP G22-05 — Weight-Volume Relationships and Conversion Factors for Soils and Aggregates of Wisconsin (WisDOT, December 2023): Table 4.11 measured conversion and expansion factors, Table 1.2 WisDOT statewide values, Table 4.8 loose and compacted unit weights
- FHWA NHI-06-088 — Soils and Foundations Reference Manual, Volume I, Table 5-4: the dry unit weight of a clean fine-to-coarse sand runs from 85 to 138 lb/ft³ on packing alone — why no single figure is offered for sand or decorative stone
- 29 CFR 1926.651(j)(2) — spoil, materials and equipment kept at least 2 ft back from the edge of an excavation, or retained: where the stockpile goes matters as much as how much of it there is